Atlantis Foundries

h

CASE STUDY

Customer: ATLANTIS FOUNDRIES
Equipment installed: Limpsfield LC9LPG 900 kW, Autoflame Mini MK8 with VSD
Fuel: LPG

SCOPE OF WORK

Supply, Install and commission a 900 kW Limpsfield LC LPG Burner with SANS 329 compliant gas train with Autoflame Mini MK8 controller The objective: to heat up the silica dust that is extracted from a manufacturing process and reduce its humidity percentage in the extraction ducting before reaching the newly installed Nederman bag filters, to prevent blockages during winter.

KEY FACTORS FOR THE SUCCESSFUL INSTALLATION

  • Pre installation testing and simulation – Provided a quick turn-around
  • Pre-planning site layout avoided any potential delays and risks.
  • Our Experience from previous projects.

BENEFIT AND COST SAVING TO SITE

The Customer doesn’t have to stop production to clean or replace blocked filters in the newly installed filter baghouse anymore! Saving on production losses and improving production output.

Contract Report