CONETECH
CASE STUDY
Customer: Conetech (Peninsula Steam)
Location: Wellington Winery, Western Cape, SA
Year: 2019
Boiler Type: I.VAR BHP 1000
Burner Type: Riello RL 70 2-stage burner
Fuel: Paraffin
SCOPE OF WORK
Supply of an I.VAR BHP 1000 Steam boiler with Riello RL 70 (2-stage), light oil burner.
The equipment is applied to the Client’s processing operations where they use the steam to reduce the amount of alcohol content of wine.
INSTALLATION DETAILS
The boiler was supplied to partner company, Peninsula Steam who installed it entirety as a containerised system. Combustion Technology commissioned the Boiler & Burner system.

Conetech,
Wellington Winery, Western Cape, SA
KEY FACTORS FOR SUCCESSFUL INSTALLATION OF KIT
This was a tried and tested burner and boiler combination. Easy plug and play system.
BENEFIT AND COST SAVING TO SITE
- A reliable system that produces steam with very little to no downtime.
- The equipment that was installed is well known for its durability features.
- The Customer expressed that we offer a very high level of service and have never let them down when they reached out for assistance.
COMMENT FROM THE CUSTOMER
Dear Combustion Technology
Thanks for supplying and perform a professional installation regarding our boiler.
Thank you for being available when we require assistance and service

Kind Regards
Gerrit Visser